Following are regulatory and technical documents on investigations, remediation and monitoring data for the Richmond Field Station Remediation and Restoration Project. The project was initiated in 1999 by order of the California Regional Water Quality Control Board San Francisco Bay Region ("the Board"). The Board has oversight authority over San Francisco Bay toxic hot spots identified by investigations completed pursuant to the Bay Protection and Toxic Cleanup Program legislation.

In May 2005, the California Environmental Protection Agency announced that the state's Department of Toxic Substances Control (DTSC) would be the new lead regulatory oversight agency for remediation and wetlands restoration work at the RFS. UC Berkeley was issued a Site Investigation and Remediation order in September 2006..

Additional historic reports will be added in the future and as new documents become available.

 
     
Regulatory Documents (Permits, Orders, Agreements, etc.)  
   
DTSC ORDER RICHMOND FIELD STATION  
  September 15, 2006 State of California Department of Toxic Substances Control Site Investigation and Remediation Order, Docket No. I/SE-RAO 0607-004 (3,051 KB pdf file)  
   
DTSC ORDER ZENECA SITE  
  September 15, 2006 State of California Department of Toxic Substances Control Site Investigation and Remediation Order, Docket No. I/SE-RAO 0607-004 (1,415 KB pdf file)  
   
BOARD ORDER:  
  October 2001 California Regional Water Quality Control Board San Francisco Bay Region Order No. 01-102 Site Cleanup Requirements for: University of California Berkeley Zeneca Inc. Meade Street Operable Unit Subunit 2 [157 KB doc file]  
   
ARMY CORPS OF ENGINEERS PERMIT:  
  June 2003 Nationwide Permit 38 Modification Request (ACOE File No. 25417S) Western Stege Marsh Remediation and Restoration Project at Richmond Field Station US Army Corpos of Engineers, Regulatory Branch, BBL [24 MB pdf file]  
     
  July 2003 Biological Assessment Report [7 MB p df file] and transmittal letter to USACE and USFWS [28 KB pdf file]  
     
  September 4, 2003 Department of the Army, Corps of Engineers, File Number 28135S- Western Stege Marsh Remediation and Restoration (Army Nationwide Permit 38 Authorization [1,213 KB pdf file]  
   
BCDC PERMIT:  
     
  June 2003 Revision to Permit No. M01-52 Western Stege Marsh Remediation and Restoration Project, Richmond California Sa n Francisco Bay Conservation and Development Commission, BBL [33 MB pdf file]  
     
  October 17, 2003 Bay Conservation and Development Commission Permit No. M01-52(b) Amendment No. One [178 KB pdf file]  
   
  June 18, 2004 Bay Conservation and Development Commission Permit No. M01-52(b) Amendment No. Two Extension [ 19 KB pdf file]  
   
CEQA Documenation  
  May 28, 2003 Richmond Field Station Remediation Project Initial Study California Environmental Quality Act [16 MB pdf file]  
   
Human Health and Ecological Risk Assessment Reports  
  November 2001 Human Health and Ecological Tiered Risk Evaluation, University of California, Berkeley, Richmond Field Station/Stege Marsh, URS [ 31MB pdf file]  
   
  November 1, 2002 Response to Comments on Human Health and Ecological Risk Assessment, letter to RWQCB [ 3,282 KB pdf file]  
   
 

Provisional Joint Health Statement Summary, The Zeneca and UC Richmond Field Station Sites, Contra Costa County Health Services Department and California Department of Health Services

 
     
   

January 18, 2006 Revision

Full Statement [160 KB pdf file]

Short Statement [132 KB pdf file]

 
       
   

June 23, 2005

Full Statement [18 KB pdf file]

Short Statement [15 KB pdf file]

 
       
  August 15, 2007 Draft Pulbic Health Statement Evaluation of Exposure to Contaminants at the University of California, Berkeley, Richmond Field Station California Department of Public Heatlh [ 3.9 MB pdf file]  
     
  September 5, 2007 Results of a Draft Public Health Evaluation about Contaminants at the UC Richmond Field Station Contra Costa County Health Services Department two page summary [113 KB pdf file]  
     
  September 27, 2007 Draft Public Health Assessment - UC Comments [1.01 MB pdf file]  
     
  March 13, 2008 ATSDR Public Health Assessment Evaluation of Exposure to Contaminants at the University of California, Berkeley, Richmond Field Station [3.7 MB pdf file]  
     
   
Back to top   
   
Investigation and Cleanup Plans and Reports  
  August 1989 Environmental Assessment of University of California Richmond Field Station Richmond, CA ensco environemental services [218 kB pdf file] Note: This document was scanned upside-down. To view right-side up go to View and rotate the document twice in either direction.  
     
  April 6, 1990 Environmental Assessment for the Proposed EPA Region 9 Laboratory at the University of California's Richmond Field Station, Jones & Stokes Associates [2 MB pdf file]  
     
 

May 21, 1990 Removal Site Evaluation of Mercury in Soil and Groundwater at Former Mercury Fulminate Facility Richmond Field Station May 21, 1990 Jonas & Associates [31 MB pdf file]  Note: This document was scanned upside-down. To view right-side up go to View and rotate the document twice in either direction.

 
     
  May 21, 1990 DRAFT Environmental Soil Sampling and Analysis Plan for Construction of EPA Laboratory at the University of California Richmond Field Station Richmond, California May 21, 1990, Jonas & Associates [35 MB pdf file]  
     
  February 22, 1991 Preliminary Risk Assessment University of California Richmond Field Station, Jonas & Associates [23 MB pdf file]  
     
  December 10, 1999 University of California, Berkeley Richmond Field Station, Field Sampling and Analysis Plan and Tiered Risk Evaluation, URS [24 MB pdf file]  
     
  December 2000, Field Sampling and Analyses Results University of California, Berkeley Richmond Field Station/ Stege Marsh, URS [33 MB pdf file]
 
   
 

November 21, 2001 Results of Additional Soil and Groundwater Investigations and Groundwater Monitoring Plan, Upland Portion of Subunit 2A, Richmond Field Station (Tasks 2A and 2B RWQCB Order No. 01-102)

Volume 1 Text, Figures Tables [6.6 MB pdf file]

Volume 2 QC and Laboratory Analytical [21 MB pdf file]

 
   
  November 21, 2001 Results of Additional Soil and Groundwater Investigations and Surface Water Monitoring Plan, MarshPortion of Subunit 2A, Richmond Field Station (Tasks 3A and 3B RWQCB Order No. 01-102) [6.1 MB pdf file]  
   
  February 28, 2002 Workplan for Additional Soil and Groundwater Investigation Upland Portion of Subunit 2B Richmond Field Station (Tasks 4A, RWQCB Order No. 01-102) [4 MB pdf file]  
   
  February 28, 2002 Workplan for Additional Sediment and Surface Water Sampling Marsh Portion of Subunit 2B (Task 5A RWQCB Order No. 01-102) [5MB pdf file]  
   
  PHASE 1: August 16, 2002 Remedial Design Details- Addendum Subunit 2A Meade Street Operable Unit Richmond Field Station, Richmond, California (Tasks 2D and 3D, RWQCB Order No.01-102), URS Corporation [4 MB pdf file]
 
   
  October 31, 2002 Results of Additional Soil and Groundwater Investigations Upland Portion of Subunit 2B Richmond Field Station (Task 4B RWQCB Order No. 01-102) [14 MB pdf file]  
   
  PHASE 1: November 6, 2002 Remedial Design Details- Addendum 2 Mercury Treatability Study Subunit 2A Meade Street Operable Unit Richmond Field Station, Richmond, California (Tasks 2D and 3D, RWQCB Order No.01-102), URS Corporation [921 KB pdf file]
 
     
  December 17, 2002 Conceptual Remedial Action Plan Marsh Portion of Subunit 2B, Richmond Field Station, Richmond California (Tasks 5B, RWQCB Order No. 01-102) [ 28 MB pdf file]  
   
  PHASE 1: September 4, 2003 Implementation Report, Phase 1, Subunit 2A Meade Street Operable Unit, University of California Berkeley, Richmond Field Station, Richmond California (Tasks 2E and 3E, RWQCB Order No.01-102), URS Corporation [148 MB pdf file]
 
   
  PHASE 2: April 15, 2003 Remedial Action Plan Phase 2 Subunits 2A and 2B Marsh, Meade Street Operable Unit, University of California Berkeley, Richmond Field Station, Richmond California (Task 5C, RWQCB Order No.01-102) [10 MB pdf file]
 
   
  PHASE 2: December 3, 2004 Implementation Report Phase 2 – Subunit 2A & 2B Meade Street Operable Unit, University of California Berkeley, Richmond Field Station, Richmond California (Tasks 2E, 3E and 5D, RWQCB Order No.01-102) [19 MB pdf file]
 
   
  PHASE 3: July 13, 2004 Remedial Action Plan- Phase 3 Upland Portion of Subunit 2B Meade Street Operable Unit, University of California Berkeley, Richmond Field Station, Richmond California (Tasks 4B and 4C, RWQCB Order No.01-102), BB: [9 MB pdf file]
 
   
  PHASE 3: June 16, 2005 Implementation Report Phase 3 Upland Portion of Subunit 2B Meade Street Operable Unit, University of California Berkeley, Richmond Field Station, Richmond California (Task 4D, RWQCB Order No.01-102) [63 MB pdf file]
 
   
  FUTURE PHASES: June 3, 2005 Draft Technical Report Conceptual Remedial Action Plan – Addendum Marsh Portion of Subunit 2B Richmond Field Station University of California Berkeley Richmond, California, BBL [42 MB pdf file]
 
     
  June 21, 2005 Purple Ooze Photos

August 19, 2005 DTSC Report on "Purple Ooze
"
 
     
  December 8, 2005 Revised Technical Specifications for Well Destructions University of California Berkeley - Richmond Field Station [8.1 MB pdf file]  
     
  March 8, 2006 Well Closure Documentation Report University of California Berkeley - Richmond Field Station, Stellar Environmental [19 MB pdf file]  
     
  October 31, 2 006 Health and Safety Plan Addendum, University of California, Berkeley Richmond Field Station, Richmond California, Tetratech EM Inc. [1.0 MB  
     
  November 2,, 2006 Field Implementation Plan for Surface Water, Stormwater and Sediment Monitoring, University of California, Berkeley Richmond Field Station, Richmond California, Tetratech EM Inc. [1.0 MB pdf file]  
     
  December 18, 2006 Surface Water, Sediment and Stormwater Monitoring Report University of California Richmond Field Station TETRATECH EMI [3,046 KB pdf file]  
   
 

April 5, 2007 Current Conditions Report (CCR) University of California Richmond Field Station TETRATECH EMI Due to the large l108 MB pdf file]

Due to the large size of this document has also been split and is available in the following two sections:

CCR Text, Figures and Tables [19 MB pdf file]

CCR Appendixes [33 MB pdf file]

 
 

 

 
  August 24, 2007 Final Memorandum for a Time-Critical Removal Action at the Former Forest Products Laboratory Wood Treatment Laboratory Tetratech EM inc. [1.4 MB pdf file]  
     
  September 17, 2007 DTSC Letter Approval for Forest Products Laboratory TCRA Implementation [16 KB pdf file]  
     
  September 17, 2007 DTSC Notice of Exemption for Former Forest Products Laboratory Wood Treatment Laboratory TCRA Implementation [372 KB pdf ile]  
     
  September 20, 2007 Soil Confirmation and Perimeter Air Monitoring Plan for Time Critical Removal Action at the Former Forest Products Laboratory Wood Treatment Laboratory [264 KB pdf file]  
     
  September 21, 2007 DTSC Letter Approval for Forest Products Laboratory TCRA Soil Confirmation and Perimeter Air Monitoring Plan [33 KB pdf file]  
     
  October 1- 30, 2007 DTSC Public Notice of Public Comment Period for Time Critical Removal Action at the Former Forest Products Laboratory Wood Treatment Laboratory [58 KB pdf file]  
     
  October 18, 2007 DTSC Comment Letter on the April 2, 2007 Draft Current Conditions Report [1.9 MB psf file]  
     
  October 23, 2007 DTSC Approval Letter for Use of MSRI Soil to Backfill TCRA Excavation [17 KB pdf file]  
     
  December 20, 2007 UC Berkeley Draft Response to Comments on the April 2, 2007 Draft Current Conditions Report [684 KB pdf file] and Transmittal Letter [16 KB pdf file]  
     
  February 13, 2008 Sampling Results for Western Stege Marsh Near-Surface Samples [1,320 KB pdf file]  
     
  February 13, 2008 Sampling Results for Western Transition Area Surface Soil Samples [1,430 KB pdf file]  
     
  March 14, 2008 Implementation Summary Report for a Time-Critical Removal Action at the Former Forest Products Laboratory Wood Treatment Laboratory University of California, Berkeley, Richmond Field Station, Richmond, California [24 MB pdf file]  
     
  March 18, 2008 Sampling Results for Surface Soil in the Pampas Grass Area near Building 201, University of California, Berkeley, Richmond Field Station, Richmond, California [423 KB pdf file]  
     
  April 9, 2008 DTSC Approval Letter of the March 14, 2008 Implementation Summary Report for a Time-Critical Removal Action at the Former FOrest Products Laboratory Wood Treatment Laboratory [18 KB pdf file]  
     
Monitoring and Management Reports and Plans (see also Restoration page)  
  January 2004 Invasive/Exotic Vegetation Management Plan, BBL [2 MB pdf file]  
     
  August 2004 Western Stege Marsh Restoration Project Monitoring Plan, BBL [6MB pdf file]  
     
  December 3, 2004 Groundwater, Surface Water, and Sediment Monitoring Plan, Subunit 2, Meade Street Operable Unit, BBL [12 MB pdf file]  
     
  August 2005 Western Stege Marsh Restoration Project Year 1 Monitoring Report [17 MB pdf file]  
     
  February 16, 2007 Interim Soil Management Plan for the Upland and Transition Areas, University of California, Berkeley, Richmond Field Station, Tetratech [10.6 MB pdf file]  
     
  March 15, 2007, DTSC Comments to Interim Soil Management Plan [119 KB file]  
     
  May 16, 2007 "Pyrite Cinder- containing Soils Management Procedures" letter report to DTSC [48 KB pdf file] and attachment "Regulatory Status of Soils Excavated During Replacement of Old Sewer Lines" (December 1993 DTSC) and "In- trench Reuse of Contaminated Trench Spoils from Utility Excavations" (SF RWQCB September 1995) [708 KB pdf file]  
     
  May 25, 2007 Concurrence letter from DTSC on Pyrite Cinder- containing Soils Management Procedures [15 KB pdf file]  
     
  August 10, 2007 Botanical Survey Report, URS Corp. [11.7 MB pdf file]  
     
  November 15, 2007 Year 2 Monitoring Report Western Stege Marsh Restoration Program [17 M pdf file] and Transmittal Letter [47 KB pdf file]  
     
   